Technological features of arrangement Continuous Flight Auger piles (CFA) in clay soils
Main Article Content
Abstract
Recently bored piles are widespread. Bored piles are produced by drilling borehole with its subsequent concreting and reinforcement. The main complication in the manufacture of these piles is to ensure the stability of the borehole walls while filling them with concrete. Therefore, to prevent the collapse of soil, casings that deepened during drilling borehole with auger are used. But the use of casing complicates and slows the arrangement of bored piles.
Purpose of the work is to analyse the options on the arrangement of СFA piles and assess their impact on the quality of piles shaft. To achieve this goal using the method of statistical data (eg. torque auger, concrete mix feed pressure, speed of elevation the screw) obtained from the drilling machine for the production of СFA piles.
The main key parameters controlled at the arrangement of СFA piles are raising auger speed and the supply pressure of the concrete mixture. These two parameters form the pile body. So if the first case raising the auger speed will be low and the supply pressure of concrete will be large - it turns piles larger diameter compared to the project size, leading to cost overruns of concrete and appearing of negative friction effect. In the second case, by contrast, the rate of uplift increases and pressure decreases - then we get smaller pile diameter, which can cause the collapse of the borehole walls and reduce the protective level along the pile length to the reinforcing frame and therefore СFA piles project load carrying capacity will not be provided. If the above two named cases occur regularly along the length of the piles, the piles are excluded from the work of the foundation slab.
It is shown that in the group of piles medium supply pressure of concrete mix while constructing into semi-solid clay is less than the standard value 0,1MPa and concrete overrun does not exceed 12%. Maximum cost of concrete overruns is 16%, which is less than the allowable standards - 26%. This fact is expedient to consider during designing and constructing piles.
Conducted control of Continuous Flight Auger piles in clay soils (P <0,1MPa and k <= 1,16) confirmed the continuity of the shaft and geometric design size.
Article Details
This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors are published in this journal, agree to the following conditions:
Authors reserve the right to authorship of their work and transfer the journal the right of the first publication of this work under the terms of the Creative Commons Attribution License, which allows other persons to freely distribute published work with mandatory reference to authors original work and the first publication of work in this journal.
The authors have the right to enter into independent additional agreements on the non-exclusive dissemination of the work in the form in which it was published by this journal (for example, to post work in the electronic repository of the institution or to publish as part of a monograph), provided that the reference to the first publication of the work in this journal is maintained.
The journal's policy allows and encourages the authors to place the manuscript of the work on the Internet (for example, in the institutions' storehouses or on personal websites), both for presenting this manuscript to the editorial office and during its editorial processing, as this contributes to the creation of productive scientific discussion and positively affects the efficiency and dynamics of citing the published work (see The Effect of Open Access).
References
DSTU-N B V.2.1-28:2013 Nastanova shhodo provedennya zemlyanyx robit, ulashtuvannya osnov ta sporudzhennya fundamentiv. (2013). Kyiv: Minregionbud Ukrayiny, 88 (in Ukrainian).
Osnovy ta fundamenty sporud. Zmina 1: DBN V.2.1–10–2009. (2011). Kyiv: Minregionbud Ukrayiny, 55 (in Ukrainian).
Boyko I.P., Delnik A.E., Kozak A.L., Orlenko N.I. (1990). Soprotivlenie prosadochnyih gruntov dlya rascheta buroyinektsionnyih svay [Resistance of collapsible soils to calculate continuous flight auger piles]. Respublikanskiy mezhve-domstvennyiy nauchno-tehnicheskiy sbornik «Osnovaniya i fundamentyi». Kyiv: Budivelnik, 223, 5-9 (in Russian).
Boyko I.P., Karpenko Yu.V., Novofastovskyi S.M. (2004) Metody vyprobuvan gruntiv za dopomohoiu buroiniektsiinoi pali velykoho diametru [Methods of soil tests using large-diameter continuous flight auger piles]. Osnovy i fundamenty: Mizhvidomchyi naukovo-tekhnichnyi zbirnyk. Kyiv: KNUBA, 328, 11-16 (in Ukrainian).
Zotsenko L.M., Levchenko V.P., Bida S.V., Perederiy M.F. (2009) Osoblivosti vlashtuvannya buroinektsiynih pal u vodonasichenih pischanih gruntah [Features of the installation continuous flight auger piles in water-saturated sandy soils]. Zb. nauk. prats (Galuzeve mashinobuduvannya, budIvnitstvo). Poltava: PNTU,76 (in Ukrainian).
Zotsenko L.M., Levchekno V.P., Zotsenko V.M (2008) Dosvid vikoristannya buroinektsiynih pal v vodonasichenih lesovih gruntah [Experience of using continuous flight auger piles in saturated loessial soils]. Stroitelnaya nauka i tehnika. Minsk, 3(18), 23 (in Ukrainian).
Levchenko V.P. (2010) EksperimentalnI dosli-dzhennya vplivu obtisnennya betonu pri vlashtuvannI buroinektsiynih pal [Experimental investigations of the influence of concrete compression on the arrangement of continuous flight auger piles]. Stroitelstvo, materialovedenie, mashinostroenie: Sb. nauch. Trudov. DnIpropetrovsk PGASA, 74, 243-251 (in Ukrainian).
Nikitenko M.I. (2007) Buroinektsionnyie ankeryi i svai pri stroitelstve i rekonstruktsii zdaniy i sooruzheniy: monografiya [Continuous flight auger anchors and piles in the construction and renovation of buildings and structures: a monograph] Minsk: BNTU, 580 (in Russian).